Our plants

In 2006 FRI-EL Green Power set up FRI-EL Acerra S.r.l. and concluded the authorization procedure to put into function the liquid Biomass thermoelectric plant in Acerra (Napoli) in order to produce electrical energy. The Acerra plant started working in 2008 and has a total installed capacity of 74,8 MW.  The power size of the thermo-electric plant is the second largest in Europe among those fuelled by vegetal oil.

  SITE REGION INSTALLED
CAPACITY
INAUGURATION
YEAR
biomassa_2_2_acerra ACERRA (NA) Campania 74,8 MW
2008
  
       
  TECHNICAL DATA
    
biomassa_2_2_punto
FIRM: FRI-EL Acerra S.r.l.
biomassa_2_2_punto CAPACITY: 74,8 MW, of which:
first cycle: 68,3 MW / second cycle: 6,5 MW
biomassa_2_2_punto PRODUCTION: about 600.000 MWh / year
biomassa_2_2_punto RAW MATERIALS: palm oil
biomassa_2_2_punto ENGINES: diesel
biomassa_2_2_punto INVESTMENT: € 85 million